|
National Maritime Development Scheme
Chennai Port is
contemplating to carry out the following Major Projects under the
National Maritime Development scheme. Phase - I
Development Of Second
Container Terminal On BOT Basis. (Estimated Cost Rs.492 Crores.)
An estimate of Rs.491.76
crores was accorded in-principle approval by the Ministry during March
2005 to develop a Second Container Terminal at EQ and SQIII. Out of 11
qualified applicants, only 3 offers were received on 7.11.05.
Technical bids were opened and clarifications were obtained from the
bidders. Only one bidder viz. PSA – SICAL Consortium qualified under
RFP and their financial bid was opened on 04.09.2006. The bidder
offered 45.801% as revenue share to the Port. After approval of the
Government on 31.10.2006, the letter of intent was issued on 05.11.06.
The 30 year licence agreement will be signed by the end of December
2006. The Project will ultimately increase the container handling
capacity of the Port by 8 lakh TEUs per annum.
Dedicated Elevated
Expressway To Maduravoyal Upto Nh4.Estimated Cost Of Rs.750 Crores
To expedite the movement
of cargo, a scheme for providing a Dedicated Elevated Expressway from
the Southern Gate of Chennai Port to Maduravoyal leading to the NH4
was formulated at an estimated cost of Rs.750 crores. After examining
various alternatives, the proposal for a four-lane corridor along
Poonamallee High Road was recommended and the Feasibility Report was
submitted in March 2006 to the Ministry of Shipping, Road Transport &
Highways with a request to constitute a SPV comprising NHAI, Chennai
Port and Tamilnadu Government to implement the proposal on the
direction of the Ministry NHAI has recently commissioned a detailed
feasibility study for the project. This proposal will improve the
connectivity of the port and facilities smooth movement road bound
cargo to and from Chennai Port.
Modernisation Of Chennai
Port: (Estimated Cost Rs. 200 Crores)
In order to facilitate a
long-term Development plan for Chennai Port, the above Scheme was
included at an estimated cost of Rs.200 crores to be executed in
phases over a period of 3-5 years. As a first step, an estimate of
Rs.40 Crores was approved during June 2005, for realignment of the
rail and road network inside the Port for quicker movement of cargo.
Old structures in the proposed alignment of the road / railways are
also being dismantled. This will enable upgrading of the road network
inside the Port from the southern and (Gate No.10) to the northern end
(Gate No.1) The following major works are under progress at a total
cost of Rs.10 crores.
-
Widening of fire
fighting road from Gate No.8 to 10 including the road adjacent to
the Office of DCOS(D).
-
Widening of South
Spring Heaven Road from its junction in the SQ II road near
DLB canteen upto Gate No.8.
-
Widening or Ore berth
road in Bharathi Dock area
-
Widening of peripheral
road in Bharathi Dock area and
-
Providing storm water
drainage arrangements in Marshalling and Coal Yard in South Zone of
Chennai port.
-
Modification works in
the shed at Eastern Side of Timber Pond are in SQ-I and construction
of toilet blocks.
-
Re-alignment of down
mainline from CI point to D6 point in Marshalling Yard.
Based on the directions
of the Ministry, a contract for Development of a Business Plan for
Chennai Port Trust was awarded to M/s.Deloitte Touche Tohmatsu India
Pvt., Baroda in April 2006.. The preparation of Business Plan for all
ports is being coordinated by the central adviser, port of Rotterdam.
M/S.Deloitte submitted their inspection report and later then draft
interim report was submitted to the central adviser on 11.12.06. Based
on the recommendations of the central adviser, the consultant will
proceed further.
Creating Back Up Area Off
Dock Cfs & Parking Area: (Estimated Cost Rs.10 Crores)
A proposal to acquire a
60-acre of land at Sathangadu from CMDA for setting up off-dock CFS
and parking area was included in the NMDP. However due to delay in the
land acquisition, an alternative was proposed for creating this
facility at Tondiarpet Housing Colony by dismantling some old
quarters. A proposal was drawn up through RITES for the scheme and
approval of Southern Railway is awaited. This will make available a
buffer storage area for catering to the increasing volumes of cargo
likely to be handled at Chennai port in the next two decades. In
addition, the Port is also following up the matter with the Government
of Tamilnadu / CMDA and they have agreed to provide an area of 25
acres for the offdock CFS, after evicting some of the existing
allottees. The increase in the railway share of containers will boost
the efficiency of container handling operations.
Creation Of Additional
Storage Open Area By Reclamation: (Estimated Cost Rs.200 Crores)
With a view to developing
additional open area, proposals have been drawn up for reclaiming
about 68 hectares of land at two locations, viz., at the area north of
sand screen to an extent of 8 hectares and near Gate No.1 to the north
of Bharathi Dock to an extent of 60 hectares. The contract for the
first stage reclamation work is in progress at an estimated cost of
rs.10.02 crores after formal CRZ clearance was received from MOE&F in
Feb’06. The work on the reclamation further north will be taken up
after completion of the mathematical model study and CRZ clearance of
MOE&F.
Dredging The Channels,
Bharathi Dock & Dr. Ambedkar Dock: (Estimated Cost Rs.143 Crores)
As part of the
Government’s initiative to provide a minimum depth of 14m at all major
ports, a proposal was forwarded to the Ministry for Capital Dredging
the entrance and approach channels and the Bharathi Dock to handle
SUEZMAX vessels. The Inner Harbour Basin and modernized berths at EQ
and SQ III at Dr.Ambedkar Dock will also be deepened to (-) 15.5 m CD.
Initially, a 2 year contract was awarded in Sep’06 for modernization
of JD. Further work will commence at SQ I. The dredging work will
follow after completion of the Berth Modernization work. The proposal,
which is estimated to cost Rs.143 crores was subsequently included
under NMDP.
B. Phase II Schemes;
The following schemes
will be taken up in due course:
-
Multilevel Car parking
terminal
-
JV with MEPZ for
off-dock ICD
-
JV with Ennore Port for
handling dry bulk cargo.
<
Top > |